PJM-AF2-370
20 MW storage in Delaware, IN · In queue since March 2020 · Proposed COD December 2023
20 MW
Capacity
1
Components
Battery
6y 2m
In Queue
System Impact Study
IA Status
COD target: 2023
Total Duration
3y 9m
Schedule
28 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-31
PJM-AF2-370 is a proposed 20 MW battery storage project located in Delaware County, Indiana. The project is interconnected within the PJM Interconnection queue, having entered the queue on March 31, 2020. The proposed commercial operation date is December 31, 2023. The project's interconnection status is currently in the System Impact Study phase. The interconnecting utility is AEP, and the point of interconnection is the Delaware-Royerton 138 kV substation.
The development project consists solely of battery storage, with a total capacity of 20 MW.
Generated from interconnection queue and public data sources
State
IN
County
Delaware
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Delaware-Royerton 138 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AF2-370