GGC Solar
2.65 MW hybrid in Dorchester, MD · In queue since March 2020 · Proposed COD March 2024
2.65 MW
Capacity
1
Components
Solar
6y 2m
In Queue
System Impact Study
IA Status
COD target: 2024
Total Duration
4 years
Schedule
25 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-03-31
The GGC Solar project is a proposed solar and battery hybrid project located in Dorchester County, Maryland. The project, with a total capacity of 2.65 MW, consists of 2.65 MW of solar generation. It is listed in the PJM interconnection queue as project PJM-AF2-378, with an entry date of March 31, 2020, and a proposed commercial operation date of March 31, 2024. The project's interconnection status is currently in the System Impact Study phase.
The proposed project is interconnected to the distribution grid of Delmarva Power & Light (DPL) at the Cambridge 12 kV point of interconnection. The project is currently listed as active in the PJM interconnection queue. The developer is not specified in the queue data.
Generated from interconnection queue and public data sources
State
MD
County
Dorchester
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
DPL
Entity
PJM
Service Type
—
Point of Interconnection
Cambridge 12 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- WCAMBRI2138 KV T1
- POI Substation
- West Cambridge Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about GGC Solar