GGC Solar (PJM-AF2-378) — Project Summary

Queue ID
PJM-AF2-378
Capacity
2.65 MW
Technology
Solar+Battery
Status
active
Location
Dorchester, MD
Region
PJM
Developer
IA Status
System Impact Study

GGC Solar

PJM-AF2-378BetaActiveSolarBatteryPJMLBNL + Live

2.65 MW hybrid in Dorchester, MD · In queue since March 2020 · Proposed COD March 2024

2.65 MW

Capacity

1

Components

Solar

6y 2m

In Queue

System Impact Study

IA Status

COD target: 2024

Interconnection

Total Duration

4 years

Schedule

25 months past proposed COD

Impact Study25%
Queue EntryMar 31, 2020

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-03-31

About

The GGC Solar project is a proposed solar and battery hybrid project located in Dorchester County, Maryland. The project, with a total capacity of 2.65 MW, consists of 2.65 MW of solar generation. It is listed in the PJM interconnection queue as project PJM-AF2-378, with an entry date of March 31, 2020, and a proposed commercial operation date of March 31, 2024. The project's interconnection status is currently in the System Impact Study phase.

The proposed project is interconnected to the distribution grid of Delmarva Power & Light (DPL) at the Cambridge 12 kV point of interconnection. The project is currently listed as active in the PJM interconnection queue. The developer is not specified in the queue data.

Generated from interconnection queue and public data sources

Project Details

State

MD

County

Dorchester

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

DPL

Entity

PJM

Service Type

Point of Interconnection

Cambridge 12 kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
PJM
Trading Hub
WESTERN HUB
Hub Confidence
HIGH
Nearest Node (Estimated)
WCAMBRI2138 KV T1
POI Substation
West Cambridge Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about GGC Solar