Project PJM-AF2-388 — Project Summary

Queue ID
PJM-AF2-388
Capacity
200 MW
Technology
Wind
Status
active
Location
Blackford, IN
Region
PJM
Developer
IA Status
System Impact Study

PJM-AF2-388

PJM-AF2-388BetaActiveWindPJMLBNL

200 MW generation in Blackford, IN · In queue since March 2020 · Proposed COD December 2023

200 MW

Capacity

1

Components

Wind

6y 2m

In Queue

System Impact Study

IA Status

COD target: 2023

Interconnection

Total Duration

3y 9m

Schedule

29 months past proposed COD

Impact Study25%
Queue EntryMar 31, 2020

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-12-15

About

PJM-AF2-388 is a proposed 200 MW wind energy project located in Blackford County, Indiana. The project, which consists of 200 MW of wind generation, is in the PJM interconnection queue as of March 31, 2020. The proposed commercial operation date is December 15, 2023. The interconnecting utility is AEP.

The project's interconnection status is currently in the System Impact Study phase. The point of interconnection is the Keystone-Desoto 345 kV line.

Generated from interconnection queue and public data sources

Project Details

State

IN

County

Blackford

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

AEP

Entity

PJM

Service Type

Point of Interconnection

Keystone-Desoto 345 kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
PJM
Trading Hub
AEP-DAYTON HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.