PJM-AF2-396
200 MW hybrid in Cass, MI · In queue since March 2020 · Proposed COD December 2023
200 MW
Capacity
1
Components
Solar
6y 2m
In Queue
System Impact Study
IA Status
COD target: 2023
Total Duration
3y 9m
Schedule
28 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-31
PJM-AF2-396 is a proposed 200 MW hybrid solar and battery project located in Cass County, Michigan. The project consists of 200 MW of solar generation. It is in the PJM interconnection queue, having entered on March 31, 2020, with a proposed commercial operation date of December 31, 2023. The interconnection utility is AEP.
The project's interconnection status is currently in the System Impact Study phase.
Generated from interconnection queue and public data sources
State
MI
County
Cass
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Stinger 138 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- POI Substation
- Tiger