Fall Creek Energy Storage
80 MW storage in Madison, IN · In queue since March 2020 · Proposed COD January 2028
80 MW
Capacity
1
Components
Battery
6y 2m
In Queue
IA Executed
IA Status
COD target: 2028
Total Duration
7y 10m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2028-01-15
The Fall Creek Energy Storage project is a proposed 80 MW battery storage project located in Madison County, Indiana. The project is in the PJM interconnection queue as entry PJM-AF2-408, with a queue entry date of March 31, 2020, and a proposed commercial operation date of January 15, 2028. The interconnection agreement for the project has been executed.
The project, which will interconnect at the Fall Creek 138 kV point of interconnection, has been the subject of recent news coverage.
Generated from interconnection queue and public data sources
State
IN
County
Madison
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Fall Creek 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- POI Substation
- Fall Creek Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesNo ask pi reports yet for this entity.
ask pi about Fall Creek Energy Storage