Woods Landing Energy Storage
250 MW storage in Atlantic, NJ · In queue since March 2020 · Proposed COD January 2030
250 MW
Capacity
1
Components
Battery
6y 2m
In Queue
IA Executed
IA Status
COD target: 2030
Total Duration
9y 10m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2030-01-31
Woods Landing Energy Storage is a proposed 250 MW battery storage project located in Atlantic County, New Jersey. The project is in the PJM interconnection queue as entry PJM-AF2-413, with a queue entry date of March 31, 2020, and a proposed commercial operation date of January 31, 2030. The project's interconnection agreement has been executed. The interconnecting utility is JCPL.
The Woods Landing Energy Storage project has been mentioned in recent industry news.
Generated from interconnection queue and public data sources
State
NJ
County
Atlantic
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
JCPL
Entity
PJM
Service Type
—
Point of Interconnection
Raritan River 230 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- SAYREVIL115 KV MCSA
- POI Substation
- Raritan River (Sayreville) Substation