WA-Cochecton 2
20 MW generation in Adams, PA · In queue since March 2020 · Proposed COD December 2027
20 MW
Capacity
1
Components
Solar
6y 2m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
7y 9m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-12-31
The WA-Cochecton 2 project is a proposed 20 MW solar generation project located in Adams County, Pennsylvania. The project is in the PJM interconnection queue as entry PJM-AF2-417, with a queue entry date of March 31, 2020. The proposed commercial operation date is December 31, 2027. The project's interconnection agreement has been executed.
The proposed project, which will interconnect with PPL at the West Damascus Tap-West Damascus 69 kV point of interconnection, is currently listed as active within the PJM queue.
Generated from interconnection queue and public data sources
State
PA
County
Adams
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PPL
Entity
PJM
Service Type
—
Point of Interconnection
West Damascus Tap-West Damascus 69 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about WA-Cochecton 2