Shamrock Energy Center
20 MW generation in Northumberland, PA · In queue since March 2020 · Proposed COD February 2027
20 MW
Capacity
1
Components
Solar
6y 2m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
6y 11m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-02-01
The proposed Shamrock Energy Center is a 20 MW solar generation project located in Northumberland County, Pennsylvania. The project, under development within the PJM Interconnection region, entered the PJM queue as project AF2-424 on March 31, 2020. The proposed commercial operation date is February 1, 2027.
The Shamrock Energy Center has an Interconnection Agreement (IA) executed with PJM. The project is interconnected to the grid at the Reed-Reed Tap #1 69 kV point of interconnection, and it is within the service territory of utility PPL. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
PA
County
Northumberland
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PPL
Entity
PJM
Service Type
—
Point of Interconnection
Reed-Reed Tap #1 69 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM