Frosty Valley Energy Center
20 MW generation in Anne Arundel, MD · In queue since March 2020 · Proposed COD January 2027
20 MW
Capacity
1
Components
Solar
6y 2m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
6y 10m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-01-15
The proposed Frosty Valley Energy Center is a 20 MW solar generation project located in Anne Arundel County, Maryland. The project is in the PJM interconnection queue as entry PJM-AF2-434, with a queue entry date of March 31, 2020, and a proposed commercial operation date of January 15, 2027. The interconnection agreement for the project has been executed.
The project, which is being developed within the PJM service area, consists of 20 MW of solar photovoltaic generation. The point of interconnection is the Columbia-Geisinger Tap #1 69 kV line. The utility is PPL.
Generated from interconnection queue and public data sources
State
MD
County
Anne Arundel
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PPL
Entity
PJM
Service Type
—
Point of Interconnection
Columbia-Geisinger Tap #1 69 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.