PJM-AF2-441
200 MW storage in Cook, IL · In queue since March 2020 · Proposed COD May 2024
200 MW
Capacity
1
Components
Battery
6y 2m
In Queue
Feasibility Study
IA Status
COD target: 2024
Total Duration
4y 2m
Schedule
23 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-05-31
PJM-AF2-441 is a proposed 200 MW battery storage project located in Cook County, Illinois. The project, which is in the PJM interconnection queue, entered the queue on March 31, 2020, with a proposed commercial operation date of May 31, 2024. The project's interconnection status is currently in the Feasibility Study phase.
The proposed project is located within the ComEd service territory. The point of interconnection is the Burnham 138kV substation.
Generated from interconnection queue and public data sources
State
IL
County
Cook
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Burnham 138kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- 55 HEGEW138 KV TR71 12
- POI Substation
- ComEd Burnham 138kV-345kV Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.