PJM-AG1-007
9.4 MW generation in Edgecombe, NC · In queue since May 2020 · Proposed COD June 2028
9.4 MW
Capacity
1
Components
Solar
6 years
In Queue
System Impact Study
IA Status
COD target: 2028
Total Duration
8y 1m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-01
PJM-AG1-007 is a proposed solar generation project with a total capacity of 9.4 MW, located in Edgecombe County, North Carolina. The project is in the PJM interconnection queue, having entered the queue on May 1, 2020. The proposed commercial operation date is June 1, 2028. Dominion is the interconnecting utility. The project's interconnection status is currently in the System Impact Study phase.
The development project consists of a single 9.4 MW solar component. The point of interconnection is the Tar River 12.5 kV. The project is currently listed as active within the PJM queue.
Generated from interconnection queue and public data sources
State
NC
County
Edgecombe
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Tar River 12.5 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- 955 RIVE16 KV RV-2
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG1-007