PJM-AG1-008
126 MW generation in Hertford, NC · In queue since May 2020 · Proposed COD December 2024
126 MW
Capacity
1
Components
Solar
6 years
In Queue
Feasibility Study
IA Status
COD target: 2024
Total Duration
4y 7m
Schedule
17 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-15
The proposed PJM-AG1-008 project is a 126 MW solar generation facility located in Hertford County, North Carolina. The project, which is in the PJM interconnection queue, was entered on May 1, 2020, and has a proposed commercial operation date of December 15, 2024. Dominion is the interconnecting utility.
The project's interconnection status is currently in the Feasibility Study phase. The point of interconnection is the Tunis-Mapleton 115 kV line. The project has appeared in recent news coverage regarding renewable energy development in the region.
Generated from interconnection queue and public data sources
State
NC
County
Hertford
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Tunis-Mapleton 115 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG1-008