Harvey Solar I
85 MW generation in Licking, OH · In queue since June 2020 · Proposed COD January 2029
85 MW
Capacity
1
Components
Solar
5y 11m
In Queue
Facility Study
IA Status
COD target: 2029
Total Duration
8y 7m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-01-15
Harvey Solar I is a proposed 85 MW solar generation project located in Licking County, Ohio. The project, developed under utility AEP, is currently active in the PJM interconnection queue as entry AG1-024, with a queue entry date of June 1, 2020. Its proposed commercial operation date is January 15, 2029.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the Centerburg 138 kV substation. The Harvey Solar I project has appeared in recent news coverage regarding renewable energy development in Ohio.
Generated from interconnection queue and public data sources
State
OH
County
Licking
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Centerburg 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Harvey Solar I