NC3 Ahoskie South Solar Project
5 MW hybrid in Hertford, NC · In queue since June 2020 · Proposed COD August 2027
5 MW
Capacity
1
Components
Solar
5y 11m
In Queue
System Impact Study
IA Status
COD target: 2027
Total Duration
7y 2m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-08-29
The proposed NC3 Ahoskie South Solar Project is a 5 MW hybrid solar and battery energy storage project located in Hertford County, North Carolina. The project, under development within the Dominion service area, consists of 5 MW of solar generation. It is listed in the PJM interconnection queue as project PJM-AG1-037, with a queue entry date of June 16, 2020.
The proposed commercial operation date for the NC3 Ahoskie South Solar Project is August 29, 2027. The project's interconnection status is currently in the System Impact Study phase. The point of interconnection is the Ahoskie 34.5 kV substation. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
NC
County
Hertford
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Ahoskie 34.5 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about NC3 Ahoskie South Solar Project