Green Meadows Solar
40 MW generation in Lawrence, PA · In queue since July 2020 · Proposed COD May 2027
40 MW
Capacity
1
Components
Solar
5y 10m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
6y 10m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-05-31
Green Meadows Solar is a proposed 40 MW solar generation project located in Lawrence County, Pennsylvania. The project is in the PJM interconnection queue as entry AG1-054, with a queue entry date of July 21, 2020. The proposed commercial operation date is May 31, 2027. The interconnection agreement has been executed.
The project is interconnected to the ATSI utility system at the Potter-Harlan 69 kV point of interconnection. The project is currently listed as active in the PJM queue.
Generated from interconnection queue and public data sources
State
PA
County
Lawrence
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ATSI
Entity
PJM
Service Type
—
Point of Interconnection
Potter-Harlan 69 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Green Meadows Solar