Bright Mountain Solar
80 MW generation in Perry, KY · In queue since July 2020 · Proposed COD January 2027
80 MW
Capacity
1
Components
Solar
5y 10m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
6y 6m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-01-27
Bright Mountain Solar is a proposed 80 MW solar generation project located in Perry County, Kentucky. The project, developed under the queue ID PJM-AG1-066, is interconnected within the PJM Interconnection queue. Its queue entry date is July 30, 2020, with a proposed commercial operation date of January 27, 2027. The interconnection agreement for the project has been executed.
The proposed project is linked to an existing operating plant, Bright Mountain Solar (EIA ID 67990). The utility involved is AEP. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
KY
County
Perry
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Bonnyman 69 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- BONNYMAN69 KV T1
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.