PJM-AG1-098
107 MW generation in Mecklenburg, VA · In queue since August 2020 · Proposed COD December 2024
107 MW
Capacity
1
Components
Solar
5y 9m
In Queue
Feasibility Study
IA Status
COD target: 2024
Total Duration
4y 4m
Schedule
17 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-01
PJM-AG1-098 is a proposed solar generation project with a total capacity of 107 MW, located in Mecklenburg County, Virginia. The project is in the PJM interconnection queue, having entered the queue on August 18, 2020, with a proposed commercial operation date of December 1, 2024. Dominion is the interconnecting utility. The project's interconnection status is currently in the Feasibility Study phase.
The development project consists solely of solar generation, with 107 MW of solar capacity. The point of interconnection is the Briery-Clover 230 kV line. The project is currently listed as active within the PJM queue.
Generated from interconnection queue and public data sources
State
VA
County
Mecklenburg
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Briery-Clover 230 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG1-098