PJM-AG1-106
23 MW generation in Northampton, NC · In queue since August 2020 · Proposed COD June 2024
23 MW
Capacity
1
Components
Solar
5y 9m
In Queue
Feasibility Study
IA Status
COD target: 2024
Total Duration
3y 10m
Schedule
23 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-06-01
The proposed project PJM-AG1-106 is a 23 MW solar generation project located in Northampton County, North Carolina. The project is in the PJM interconnection queue, having entered the queue on August 28, 2020, with a proposed commercial operation date of June 1, 2024. Dominion is the listed utility.
The project's interconnection status is currently in the Feasibility Study phase. The point of interconnection is at Thelma 230 kV.
Generated from interconnection queue and public data sources
State
NC
County
Northampton
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Thelma 230 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- THELMAEK69 KV LD_185
- POI Substation
- Thelma Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG1-106