Oak Run Solar Project
400 MW generation in Madison, OH · In queue since August 2020 · Proposed COD December 2030
400 MW
Capacity
1
Components
Solar
5y 9m
In Queue
IA Executed
IA Status
COD target: 2030
Total Duration
10y 4m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2030-12-31
The proposed Oak Run Solar Project is a 400 MW solar generation project located in Madison County, Ohio. The project is in the PJM interconnection queue as entry AG1-126, with a queue entry date of August 31, 2020, and a proposed commercial operation date of December 31, 2030. The interconnection agreement for the project has been executed. The point of interconnection is the Marysville-Flatlick 765 kV line.
The Oak Run Solar Project is being developed within the AEP utility service area. Recent news coverage indicates regulatory interest in the project.
Generated from interconnection queue and public data sources
State
OH
County
Madison
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Marysville-Flatlick 765 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26