NAES
5 MW storage in Burlington, NJ · In queue since September 2020 · Proposed COD June 2027
5 MW
Capacity
1
Components
Battery
5y 8m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
6y 9m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2027-06-30
The NAES project is a proposed 5 MW battery storage project located in Burlington County, New Jersey. The project is being developed within the PJM Interconnection region and is interconnected with PSEG at the Burlington 26 kV point of interconnection.
The project, identified as queue ID PJM-AG1-130, entered the PJM interconnection queue on September 1, 2020, and has a proposed commercial operation date of June 30, 2027. The interconnection agreement for the project has been executed.
Generated from interconnection queue and public data sources
State
NJ
County
Burlington
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PSEG
Entity
PJM
Service Type
—
Point of Interconnection
Burlington 26 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- BURLING2138 KV T1
- POI Substation
- Burlington Heights Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about NAES