PJM-AG1-135
60 MW generation in Richmond, VA · In queue since September 2020 · Proposed COD December 2024
60 MW
Capacity
1
Components
Solar
5y 8m
In Queue
System Impact Study
IA Status
COD target: 2024
Total Duration
4y 3m
Schedule
17 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-01
PJM-AG1-135 is a proposed solar generation project located in Richmond County, Virginia, within the PJM Interconnection region. The development project, with a total capacity of 60 MW, is being proposed by Dominion. It consists of a single 60 MW solar component.
The project entered the PJM interconnection queue on September 3, 2020, with a proposed commercial operation date of December 1, 2024. Its interconnection status is currently in the System Impact Study phase, and the point of interconnection is the Garner-Lancaster 115 kV line.
Generated from interconnection queue and public data sources
State
VA
County
Richmond
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Garner-Lancaster 115 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG1-135