PJM-AG1-153
75 MW storage in Brunswick, VA · In queue since September 2020 · Proposed COD December 2023
75 MW
Capacity
1
Components
Battery
5y 8m
In Queue
System Impact Study
IA Status
COD target: 2023
Total Duration
3y 3m
Schedule
29 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-01
PJM-AG1-153 is a proposed 75 MW battery storage project located in Brunswick County, Virginia. The project is in the PJM interconnection queue, having entered on September 10, 2020. Dominion is the interconnecting utility. The proposed commercial operation date is December 1, 2023.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection is the Heritage 500 kV substation.
Generated from interconnection queue and public data sources
State
VA
County
Brunswick
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Heritage 500 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- WMEDINA 138 KV NEM1FEOH
- POI Substation
- Heritage Substation