Mora Solar
60 MW generation in Carbon, PA · In queue since September 2020 · Proposed COD December 2027
60 MW
Capacity
1
Components
Solar
5y 8m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
7y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-12-31
Mora Solar is a proposed 60 MW solar generation project located in Carbon County, Pennsylvania. The development project, under the utility PPL, is interconnected within the PJM Interconnection queue as project AG1-156, with a queue entry date of September 10, 2020. The proposed commercial operation date is December 31, 2027, and the Interconnection Agreement (IA) has been executed.
The project is linked to an existing operating plant named Mora Solar (EIA ID 68810). Recent news coverage indicates regulatory interest in the project.
Generated from interconnection queue and public data sources
State
PA
County
Carbon
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PPL
Entity
PJM
Service Type
—
Point of Interconnection
Jack Frost-Lake Harmony 69 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- ACAHELA 69 KV EPLM1
- POI Substation
- Lake Harmony Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.