Club Ford Energy Center
20 MW generation in Luzerne, PA · In queue since September 2020 · Proposed COD March 2028
20 MW
Capacity
1
Components
Solar
5y 8m
In Queue
IA Executed
IA Status
COD target: 2028
Total Duration
7y 6m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-03-01
The proposed Club Ford Energy Center is a 20 MW solar generation project located in Luzerne County, Pennsylvania. The project is in the PJM interconnection queue as entry AG1-165, with a queue entry date of September 17, 2020, and a proposed commercial operation date of March 1, 2028. The interconnecting utility is PPL.
The project's interconnection agreement (IA) has been executed. The point of interconnection (POI) is the East Hazelton-Weatherly Tap 69 kV line. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
PA
County
Luzerne
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PPL
Entity
PJM
Service Type
—
Point of Interconnection
East Hazelton-Weatherly Tap 69 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM