PJM-AG1-168
15 MW generation in Nottoway, VA · In queue since September 2020 · Proposed COD October 2021
15 MW
Capacity
1
Components
Solar
5y 8m
In Queue
System Impact Study
IA Status
COD target: 2021
Total Duration
1y 1m
Schedule
55 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2021-10-15
PJM-AG1-168 is a proposed solar generation project with a total capacity of 15 MW, located in Nottoway County, Virginia. The project is in the PJM interconnection queue, with an entry date of September 16, 2020. The proposed commercial operation date is October 15, 2021. Dominion is the utility associated with the project.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection (POI) is the Lone Pine 115 kV substation.
Generated from interconnection queue and public data sources
State
VA
County
Nottoway
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Lone Pine 115 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG1-168