Morgan Street-Cochranton 34.5 kV
15 MW generation in Crawford, PA · In queue since September 2020 · Proposed COD March 2026
15 MW
Capacity
1
Components
Solar
5y 8m
In Queue
System Impact Study
IA Status
COD target: 2026
Total Duration
5y 6m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-03-31
The Morgan Street-Cochranton 34.5 kV project is a proposed 15 MW solar generation project located in Crawford County, Pennsylvania. The project is interconnected within the PJM Interconnection queue as project AG1-197, with a queue entry date of September 19, 2020. The proposed commercial operation date is March 31, 2026.
The project's interconnection status is currently in the System Impact Study phase, but is listed as suspended. The proposed point of interconnection is the Morgan Street-Cochranton 34.5 kV substation, within the PENELEC utility territory. The developer is not specified in the available data.
Generated from interconnection queue and public data sources
State
PA
County
Crawford
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Morgan Street-Cochranton 34.5 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Morgan Street-Cochranton 34.5 kV