Monmouth Solar 1
15.4 MW generation in Monmouth, NJ · In queue since September 2020 · Proposed COD December 2026
15.4 MW
Capacity
1
Components
Solar
5y 8m
In Queue
IA Executed
IA Status
COD target: 2026
Total Duration
6y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-12-31
Monmouth Solar 1 is a proposed 15.4 MW solar generation project located in Monmouth County, New Jersey. The project, developed under the queue ID PJM-AG1-223, is in the PJM interconnection queue with an entry date of September 23, 2020. The proposed commercial operation date is December 31, 2026, and the interconnection agreement has been executed. The point of interconnection is the Larrabee-Allaire 34.5 kV line.
The Monmouth Solar 1 project is listed as active in the interconnection queue and has been the subject of recent news coverage regarding its development.
Generated from interconnection queue and public data sources
State
NJ
County
Monmouth
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
JCPL
Entity
PJM
Service Type
—
Point of Interconnection
Larrabee-Allaire 34.5 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26