Boyles Run Solar
15.9 MW generation in Northumberland, PA · In queue since September 2020 · Proposed COD April 2028
15.9 MW
Capacity
1
Components
Solar
5y 8m
In Queue
IA Executed
IA Status
COD target: 2028
Total Duration
7y 7m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-04-30
Boyles Run Solar is a proposed solar generation project located in Northumberland County, Pennsylvania. The project, with a total capacity of 15.9 MW, is listed in the PJM interconnection queue as entry AG1-259, with a queue entry date of September 28, 2020. The proposed commercial operation date is April 30, 2028, and the Interconnection Agreement (IA) has been executed.
The project is linked to the existing BAI-Boyles Run-Phase 2 operating plant (EIA plant ID 67955). The designated point of interconnection (POI) is the Sunbury-Dalmatia 69 kV line, and the interconnecting utility is PPL.
Generated from interconnection queue and public data sources
State
PA
County
Northumberland
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PPL
Entity
PJM
Service Type
—
Point of Interconnection
Sunbury-Dalmatia 69 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
- POI Substation
- Hunter Substation