Boyles Run Solar
15.9 MW generation in Northumberland, PA · In queue since September 2020 · Proposed COD April 2028
15.9 MW
Capacity
1
Components
Solar
5y 8m
In Queue
IA Executed
IA Status
COD target: 2028
Total Duration
7y 7m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-04-30
The Boyles Run Solar project is a proposed 15.9 MW solar generation facility in Northumberland County, Pennsylvania. The project is located within the PJM Interconnection region and is linked to the existing BAI-Boyles Run-Phase I operating plant (EIA ID 67954).
The project, identified as queue ID PJM-AG1-260, entered the PJM interconnection queue on September 28, 2020, with a proposed commercial operation date of April 30, 2028. The interconnection agreement has been executed. The designated point of interconnection is the Sunbury-Dalmatia 69 kV line, and the interconnecting utility is PPL.
Generated from interconnection queue and public data sources
State
PA
County
Northumberland
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PPL
Entity
PJM
Service Type
—
Point of Interconnection
Sunbury-Dalmatia 69 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
- POI Substation
- Hunter Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Boyles Run Solar