PJM-AG1-297
300 MW storage in Shelby, IN · In queue since September 2020 · Proposed COD December 2023
300 MW
Capacity
1
Components
Battery
5y 8m
In Queue
Feasibility Study
IA Status
COD target: 2023
Total Duration
3y 3m
Schedule
28 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-31
PJM-AG1-297 is a proposed 300 MW battery storage project located in Shelby County, Indiana. The project is in the PJM interconnection queue, having entered on September 29, 2020. The proposed commercial operation date is December 31, 2023. The interconnection request is currently in the Feasibility Study phase.
The project, which is being developed within the AEP service territory, consists entirely of battery storage. The point of interconnection is the Hanna-Tanners Creek 345 kV line. The project is listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
IN
County
Shelby
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Hanna-Tanners Creek 345 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- TANNERSC18 KV TC3
- POI Substation
- Tanners Creek