PJM-AG1-302
300 MW generation in Pulaski, IN · In queue since September 2020 · Proposed COD January 2028
300 MW
Capacity
1
Components
Solar
5y 8m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
7y 4m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-01-15
PJM-AG1-302 is a proposed solar generation project with a total capacity of 300 MW, located in Pulaski County, Indiana. The project is in the PJM interconnection queue, having entered on September 29, 2020, with a proposed commercial operation date of January 15, 2028. The interconnecting utility is AEP. Its interconnection status is currently in the Facility Study phase.
The development project consists of 300 MW of solar photovoltaic generation. The point of interconnection is the Olive-Reynolds #1 345 kV line.
Generated from interconnection queue and public data sources
State
IN
County
Pulaski
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Olive-Reynolds #1 345 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG1-302