PJM-AG1-341
106 MW hybrid in Metcalfe, KY · In queue since September 2020 · Proposed COD June 2023
106 MW
Capacity
1
Components
Solar
5y 8m
In Queue
System Impact Study
IA Status
COD target: 2023
Total Duration
2y 9m
Schedule
35 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-06-15
PJM-AG1-341 is a proposed 106 MW hybrid solar and battery project located in Metcalfe County, Kentucky. The project, which consists of 106 MW of solar generation, is in the PJM interconnection queue, with queue entry date of September 30, 2020. The proposed commercial operation date is June 15, 2023. The interconnecting utility is EKPC.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection is the Summer Shade 161 kV substation. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
KY
County
Metcalfe
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
EKPC
Entity
PJM
Service Type
—
Point of Interconnection
Summer Shade 161 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- EIGHTY8 34.5 KV GLOVERSP
- POI Substation
- Summer Shade Substation