Project PJM-AG1-342 — Project Summary

Queue ID
PJM-AG1-342
Capacity
36 MW
Technology
Solar
Status
active
Location
Halifax, VA
Region
PJM
Developer
IA Status
Feasibility Study

PJM-AG1-342

PJM-AG1-342BetaActiveSolarPJMLBNL

36 MW generation in Halifax, VA · In queue since September 2020 · Proposed COD December 2023

36 MW

Capacity

1

Components

Solar

5y 8m

In Queue

Feasibility Study

IA Status

COD target: 2023

Interconnection

Total Duration

3y 3m

Schedule

29 months past proposed COD

Feasibility Study13%
Queue EntrySep 30, 2020

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-12-01

About

PJM-AG1-342 is a proposed 36 MW solar generation project located in Halifax County, Virginia. The project is in the PJM interconnection queue as of September 30, 2020, with a proposed commercial operation date of December 1, 2023. Dominion is the interconnecting utility. The project's interconnection status is currently in the Feasibility Study phase.

The development project consists of 36 MW of solar photovoltaic generation. It is interconnected to the grid at the Dryburg 115 kV point of interconnection. The project has appeared in recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

VA

County

Halifax

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

Dominion

Entity

PJM

Service Type

Point of Interconnection

Dryburg 115 kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
PJM
Trading Hub
DOMINION HUB
Hub Confidence
HIGH
Nearest Node (Estimated)
EDMONSON34.5 KV PINEYCSP

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project PJM-AG1-342