Flatrock Creek Solar II
100 MW generation in Allen, IN · In queue since September 2020 · Proposed COD December 2029
100 MW
Capacity
1
Components
Solar
5y 8m
In Queue
IA Executed
IA Status
COD target: 2029
Total Duration
9y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2029-12-31
The proposed Flatrock Creek Solar II project is a 100 MW solar generation facility located in Allen County, Indiana. The project is in the PJM interconnection queue as entry AG1-365, with a queue entry date of September 30, 2020. The proposed commercial operation date is December 31, 2029.
The interconnection agreement for Flatrock Creek Solar II has been executed. The project is interconnected to the AEP utility system at the Allen 345 kV point of interconnection. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
IN
County
Allen
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Allen 345 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- POI Substation
- Allen IM Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Flatrock Creek Solar II