PJM-AG1-367
100 MW generation in Delaware, IN · In queue since September 2020 · Proposed COD October 2024
100 MW
Capacity
1
Components
Solar
5y 8m
In Queue
Feasibility Study
IA Status
COD target: 2024
Total Duration
4y 1m
Schedule
18 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-10-31
PJM-AG1-367 is a proposed 100 MW solar generation project located in Delaware County, Indiana. The project is in the PJM interconnection queue, with an entry date of September 30, 2020. Its proposed commercial operation date is October 31, 2024. The interconnection status is currently in the Feasibility Study phase.
The project is being proposed within the AEP utility territory and connects to the DeSoto 345 kV point of interconnection.
Generated from interconnection queue and public data sources
State
IN
County
Delaware
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
DeSoto 345 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- POI Substation
- Desoto Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.