49.9 MW generation in Paulding, OH · In queue since September 2020 · Proposed COD March 2029
49.9 MW
Capacity
1
Components
Solar
5y 8m
In Queue
Facility Study
IA Status
COD target: 2029
Total Duration
8y 6m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-03-17
PJM-AG1-369 is a proposed solar generation project located in Paulding County, Ohio, with a total capacity of 49.9 MW. The project is in the PJM interconnection queue, having entered the queue on September 30, 2020. The proposed commercial operation date is March 17, 2029. The interconnecting utility is AEP. Its interconnection status is currently in the Facility Study phase.
The development project consists solely of solar generation, with the entire 49.9 MW capacity attributed to solar photovoltaic technology. The point of interconnection is the Logtown 138 kV substation. The project is currently listed as active within the PJM queue.
Generated from interconnection queue and public data sources
State
OH
County
Paulding
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Logtown 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- POI Substation
- Logtown Switching Station
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.