PJM-AG1-375
100 MW generation in Blackford, IN · In queue since September 2020 · Proposed COD October 2024
100 MW
Capacity
1
Components
Solar
5y 8m
In Queue
Feasibility Study
IA Status
COD target: 2024
Total Duration
4y 1m
Schedule
18 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-10-31
PJM-AG1-375 is a proposed solar generation project located in Blackford County, Indiana, within the PJM Interconnection region. The project, with a total capacity of 100 MW, consists entirely of solar photovoltaic generation. The queue entry date for PJM-AG1-375 is September 30, 2020, with a proposed commercial operation date of October 31, 2024. The interconnection utility is AEP, and the point of interconnection is the Sorenson-Desoto 345 kV line. The project's interconnection status is currently in the Feasibility Study phase.
Generated from interconnection queue and public data sources
State
IN
County
Blackford
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Sorenson-Desoto 345 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG1-375