PJM-AG1-377
20 MW generation in Centre, PA · In queue since September 2020 · Proposed COD August 2023
20 MW
Capacity
1
Components
Solar
5y 8m
In Queue
System Impact Study
IA Status
COD target: 2023
Total Duration
2y 11m
Schedule
33 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-08-15
The proposed project PJM-AG1-377 is a 20 MW solar generation project located in Centre County, Pennsylvania. The project is interconnected within the PJM Interconnection queue, having entered the queue on September 30, 2020. PJM-AG1-377 is currently undergoing a System Impact Study, with a proposed commercial operation date of August 15, 2023. The point of interconnection is at the Philipsburg 115 kV substation, and the interconnecting utility is PENELEC.
The development project consists of 20 MW of solar photovoltaic generation. It is currently listed as an active project within the PJM queue.
Generated from interconnection queue and public data sources
State
PA
County
Centre
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Philipsburg 115 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- PHILIPSB115 KV UNSH_SP
- POI Substation
- Philipsburg Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG1-377