PJM-AG1-411
100 MW storage in Van Wert, OH · In queue since September 2020 · Proposed COD September 2024
100 MW
Capacity
1
Components
Battery
5y 8m
In Queue
Feasibility Study
IA Status
COD target: 2024
Total Duration
4 years
Schedule
20 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-09-25
PJM-AG1-411 is a proposed 100 MW battery storage project located in Van Wert County, Ohio. The project, which consists of a single 100 MW battery component, is in the PJM interconnection queue as of September 30, 2020, with a proposed commercial operation date of September 25, 2024. The interconnecting utility is AEP, and the point of interconnection is Maddox Creek-RP Mone 345 kV. The project's interconnection status is currently in the Feasibility Study phase.
The development project is listed in the PJM interconnection queue under queue ID PJM-AG1-411.
Generated from interconnection queue and public data sources
State
OH
County
Van Wert
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Maddox Creek-RP Mone 345 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.