PJM-AG1-414
75 MW hybrid in Grant, IN · In queue since September 2020 · Proposed COD April 2028
75 MW
Capacity
1
Components
Solar
5y 8m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
7y 7m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-04-20
PJM-AG1-414 is a proposed 75 MW hybrid solar and battery project located in Grant County, Indiana. The project, which consists of 75 MW of solar capacity, is in the PJM interconnection queue, having entered on September 30, 2020. The proposed commercial operation date is April 20, 2028. The interconnection status is currently in the Facility Study phase.
The project is being developed within the AEP utility territory and interconnects at the Mississinewa 138 kV point of interconnection. The project has appeared in recent news coverage regarding renewable energy development in the region.
Generated from interconnection queue and public data sources
State
IN
County
Grant
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Mississinewa 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG1-414