Beckett Solar
50 MW generation in Clarke, VA · In queue since September 2020 · Proposed COD December 2028
50 MW
Capacity
1
Components
Solar
5y 8m
In Queue
IA Executed
IA Status
COD target: 2028
Total Duration
8y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-12-31
Beckett Solar is a proposed 50 MW solar generation project located in Clarke County, Virginia. The project is in the PJM interconnection queue as entry AG1-415, with a queue entry date of September 30, 2020. The proposed commercial operation date is December 31, 2028. The interconnecting utility is APS, and the interconnection agreement has been executed.
The development project consists of 50 MW of solar photovoltaic generation. It is interconnected at the Double Toll Gate-Old Chapel 138 kV point of interconnection. The project is currently listed as active in the PJM queue.
Generated from interconnection queue and public data sources
State
VA
County
Clarke
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
APS
Entity
PJM
Service Type
—
Point of Interconnection
Double Toll Gate-Old Chapel 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Beckett Solar