PJM-AG1-436
125 MW generation in Laporte, IN · In queue since September 2020 · Proposed COD December 2023
125 MW
Capacity
1
Components
Solar
5y 8m
In Queue
System Impact Study
IA Status
COD target: 2023
Total Duration
3y 3m
Schedule
28 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-31
PJM-AG1-436 is a proposed solar generation project with a total capacity of 125 MW, located in Laporte County, Indiana. The project is in the PJM interconnection queue, with an entry date of September 30, 2020. The proposed commercial operation date is December 31, 2023. The interconnection status is currently in the System Impact Study phase.
The project is being proposed within the AEP utility territory. The point of interconnection is the Olive-University Park 345 kV line.
Generated from interconnection queue and public data sources
State
IN
County
Laporte
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Olive-University Park 345 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG1-436