PJM-AG1-462
255 MW generation in Whiteside, IL · In queue since October 2020 · Proposed COD October 2023
255 MW
Capacity
1
Components
Solar
5y 7m
In Queue
Feasibility Study
IA Status
COD target: 2023
Total Duration
3 years
Schedule
32 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-10-01
PJM-AG1-462 is a proposed solar generation project with a total capacity of 255 MW, located in Whiteside County, Illinois. The project is in the PJM interconnection queue, having entered the queue on October 1, 2020, with a proposed commercial operation date of October 1, 2023. The interconnecting utility is ComEd, and the point of interconnection is Cordova 345 kV. The project's interconnection status is currently in the Feasibility Study phase.
The development project consists solely of solar generation, with the 255 MW capacity attributed to solar photovoltaic technology. The project is listed as active within the PJM queue.
Generated from interconnection queue and public data sources
State
IL
County
Whiteside
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Cordova 345 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG1-462