Project PJM-AG1-471 — Project Summary

Queue ID
PJM-AG1-471
Capacity
54 MW
Technology
Solar
Status
active
Location
KY
Region
PJM
Developer
IA Status
System Impact Study

PJM-AG1-471

PJM-AG1-471BetaActiveSolarPJMLBNL

54 MW generation in KY · In queue since September 2020 · Proposed COD October 2023

54 MW

Capacity

1

Components

Solar

5y 8m

In Queue

System Impact Study

IA Status

COD target: 2023

Interconnection

Total Duration

3y 1m

Schedule

31 months past proposed COD

Impact Study25%
Queue EntrySep 30, 2020

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-10-02

About

PJM-AG1-471 is a proposed solar generation project with a total capacity of 54 MW. The project is located in Kentucky and is being developed within the PJM Interconnection queue. The queue entry date is September 30, 2020, with a proposed commercial operation date of October 2, 2023. The project's interconnection status is currently in the System Impact Study phase. The designated point of interconnection is the Up Church-Wayne County 69 kV line.

The project is sponsored by EKPC and consists solely of solar photovoltaic generation, with the entire 54 MW capacity attributed to solar. The project is listed as active within the PJM queue.

Generated from interconnection queue and public data sources

Project Details

State

KY

County

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

EKPC

Entity

PJM

Service Type

Point of Interconnection

Up Church-Wayne County 69 kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
PJM
Trading Hub
AEP-DAYTON HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project PJM-AG1-471