Esky Solar Project
10 MW generation in Gloucester, NJ · In queue since September 2020 · Proposed COD August 2026
10 MW
Capacity
1
Components
Solar
5y 8m
In Queue
System Impact Study
IA Status
COD target: 2026
Total Duration
5y 11m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-08-31
The Esky Solar Project is a proposed 10 MW solar generation project located in Gloucester County, New Jersey. The project is listed in the PJM interconnection queue as entry AG1-499, with a queue entry date of September 30, 2020. The proposed commercial operation date is August 31, 2026.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection is at Lambs 12.47 kV. The interconnecting utility is AEC, and the entity is PJM. The project has also appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
NJ
County
Gloucester
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEC
Entity
PJM
Service Type
—
Point of Interconnection
Lambs 12.47 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Esky Solar Project