Aurora Battery Storage
10 MW storage in Will, IL · In queue since October 2020 · Proposed COD June 2028
10 MW
Capacity
1
Components
Battery
5y 7m
In Queue
IA Executed
IA Status
COD target: 2028
Total Duration
7y 8m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 6–18 months
Proposed COD: 2028-06-01
The Aurora Battery Storage project is a proposed 10 MW battery storage development in Will County, Illinois. The project, located within the ComEd service area, is interconnected to the PJM Interconnection queue as project AG1-513. The project entered the queue on October 1, 2020, and has a proposed commercial operation date of June 1, 2028.
The Aurora Battery Storage project's interconnection agreement has been executed.
Generated from interconnection queue and public data sources
State
IL
County
Will
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Aurora 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- 951 AURO13.5 KV AR5
- POI Substation
- North Aurora Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.