PJM-AG1-548
150 MW hybrid in Erie, PA · In queue since September 2020 · Proposed COD October 2022
150 MW
Capacity
1
Components
Solar
5y 8m
In Queue
Feasibility Study
IA Status
COD target: 2022
Total Duration
2y 1m
Schedule
43 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-10-31
PJM-AG1-548 is a proposed 150 MW hybrid Solar+Battery project located in Erie County, Pennsylvania. The project consists of 150 MW of solar capacity. It is in the PJM interconnection queue as of September 30, 2020, with a proposed commercial operation date of October 31, 2022. The interconnection status is currently in the Feasibility Study phase. The point of interconnection is the Erie South-Union City 115 kV line.
The proposed project is located within the PENELEC utility service area. The project is listed as active within the PJM interconnection queue.
Generated from interconnection queue and public data sources
State
PA
County
Erie
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Erie South-Union City 115 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG1-548