Scioty Solar (PJM-AG1-554) — Project Summary

Queue ID
PJM-AG1-554
Capacity
49.99 MW
Technology
Solar
Status
active
Location
Hardin, OH
Region
PJM
Developer
IA Status
IA Executed

Scioty Solar

PJM-AG1-554BetaActiveSolarPJMLBNL + Live

49.99 MW generation in Hardin, OH · In queue since September 2020 · Proposed COD October 2027

49.99 MW

Capacity

1

Components

Solar

5y 8m

In Queue

IA Executed

IA Status

COD target: 2027

Interconnection

Total Duration

7y 1m

Construction75%
Queue EntrySep 30, 2020

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2027-10-01

About

The Scioty Solar project is a proposed solar generation facility with a total capacity of 49.99 MW, located in Hardin County, Ohio. The project is being developed within the PJM Interconnection region and is interconnected with AEP at the South Kenton 138 kV point of interconnection.

The project, identified as PJM-AG1-554 in the PJM queue, entered the queue on September 30, 2020, and has a proposed commercial operation date of October 1, 2027. The interconnection agreement for the project has been executed.

Generated from interconnection queue and public data sources

Project Details

State

OH

County

Hardin

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

AEP

Entity

PJM

Service Type

Point of Interconnection

South Kenton 138 kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
PJM
Trading Hub
AEP-DAYTON HUB
Hub Confidence
HIGH
Nearest Node (Estimated)
MYSVL_EK138 KV LD_154
POI Substation
Kenton

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.