PJM-AG2-008
60 MW generation in Erie, PA · In queue since October 2020 · Proposed COD March 2023
60 MW
Capacity
1
Components
Solar
5y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
2y 5m
Schedule
38 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-03-30
PJM-AG2-008 is a proposed 60 MW solar generation project located in Erie County, Pennsylvania. The project is interconnected within the PJM Interconnection queue, having entered the queue on October 8, 2020. The proposed commercial operation date is March 30, 2023.
The interconnection agreement status is currently listed as "In Progress (unknown study)". The designated point of interconnection (POI) is the Erie South-Warren 230 kV line. The project is being developed within the PENELEC utility territory.
Generated from interconnection queue and public data sources
State
PA
County
Erie
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Erie South-Warren 230 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-008