PJM-AG2-009
20 MW generation in Erie, PA · In queue since October 2020 · Proposed COD March 2023
20 MW
Capacity
1
Components
Solar
5y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
2y 5m
Schedule
38 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-03-30
The proposed project PJM-AG2-009 is a 20 MW solar generation project located in Erie County, Pennsylvania. The project is interconnected within the PJM Interconnection queue, having entered the queue on October 8, 2020. The proposed commercial operation date is March 30, 2023.
The interconnection agreement for the project is currently listed as "In Progress (unknown study)". The point of interconnection is the Erie South-Warren 230 kV II substation, and the interconnecting utility is PENELEC.
Generated from interconnection queue and public data sources
State
PA
County
Erie
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Erie South-Warren 230 kV II
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-009